How to build an MVP: a 90-day plan

Devarko field notes · Business4 min

A minimum viable product is the smallest version of your product that does one job, start to finish, for a real customer. You build it to find out whether people want the thing before you pay for the rest. If you hold the scope firmly, most MVPs can be designed, built and launched in about twelve weeks.

This is the plan we work to, week by week, along with the mistakes that most often stretch a three-month MVP into a year.

01

Weeks 1 and 2: choose the one job

Write down who your first customer is and the one job the product does for them, from start to finish. A booking app books an appointment and confirms it. A marketplace lets one buyer pay one seller for one item. Anything that does not serve that job goes on a later list.

Then sketch every screen that job needs, including the dull ones people forget, like sign-up, password reset, the admin view and the email that confirms it worked. That list of screens is your real scope.

02

Weeks 3 and 4: design and the data

Design the main screens with care, because early users who are put off once rarely try again, but build from an existing component library instead of inventing every button. Meanwhile, design the database and user roles. They are the hardest things to change once real data is in them.

Pick technology your team already knows. You are trying to learn about customers in those twelve weeks, and a new framework eats the time you need for that.

03

Weeks 5 to 10: build in weekly slices

Get the whole job working end to end as early as you can, however rough, then improve it. Put each week's work on a staging site the founders use every Friday, so problems turn up in week six while they are cheap.

New ideas go on the later list unless the job cannot work without them. Most delays start with a feature that crept in during these six weeks.

04

Weeks 11 and 12: test and launch

Watch five to ten real users from your target group use it without help, and fix what confuses them. Set up analytics for the few events that matter, plus error monitoring and backups, before launch rather than after.

Launch first to a small group of people who asked to try it. They will tell you what is wrong while you still have room to fix it.

An MVP should do one job from start to finish, even if it does nothing else.
05

What to measure afterwards

Measure whether people finish the job and whether they come back to do it again. Sign-ups alone will flatter you. Repeat use is the sign the product solves something real.

This is the plan behind our MVP development work. We usually build on Laravel and React and Next.js, which let a small team move fast without leaving a mess to clean up later. For the money side, read what custom software really costs.

06

Why MVPs run late

Usually it is scope creep: a feature added because a competitor has it or an investor asked about it. After that come decisions nobody makes, so the team waits days for an answer, and integrations that are harder than they looked, often payments or a third-party API with poor documentation. Hold a decision meeting every week, keep a written list of what is out of scope, and try the risky integrations in the first fortnight.

07

What an MVP budget should cover

The budget has to cover design, the app or web screens, the back end and database, an admin view, testing, hosting set-up, analytics and launch support, plus a few weeks of fixes afterwards. Keep 10 to 15 percent back for what you learn along the way. A budget that covers only the screens runs out just before launch.

08

After the MVP

Let people use it for four to eight weeks before you decide what comes next. Then talk to the customers who used it most and to the ones who stopped. Plan the next phase from what they did. The feature list you wrote before launch is mostly guesswork by then.

09

Common questions

About twelve weeks for a focused web or mobile MVP with one core job, as long as nobody keeps adding to the scope. Payments, several types of user or complicated integrations push it longer.